|
| 2 Market
street |
| |
2
Market street, built by Lipman, is a complete steel structure. In Sydney's
largest fire rated paint project with a total cost of $400K, Greyton has used a
water based Promatect intumescent paint for the columns and beams providing up
to a 2 hour rating. The FRL is predominantly 60-minutes which makes this
architectural finish competitive with traditional systems. The paints were all
water based which reduces fumes and minimises drying time between coats. |
| |
| Cross City Tunnel |
| |
Greyton
was contracted by Downer Engineering and Baulderstone Haunibrook
Bilfinger+Berger to carry out extensive passive fire rating to the Cross City
Tunnel with a total contract value of $250,000. The contract consisted of over
600 services penetration seals, Promatect demountable fire and sound proof
walls, Fendolite vermiculite spray to ducts and essential services, access
panels and fire doors and fire rated bulk heads around essential services. Most
of the fire barriers had to be designed for a minimum four hour fire resistant
level. All work was completed to a high standard and strict programme set out by
Downer and BHBB. Greyton can provided contacts for both companies if references
for the above works are required. Please click the 'tunnel specialist' to
see the photos of our works.
|
| |
| Chatswood Substation Energy Australia |
| |
Following
some serious sub substation fires Energy Australia has taken action to protect
their cables with various fire rated products. This can be done with spray
painted ablative and intumescent coating directly to the cables or the
construction of ducts that provide insulation and integrity protection. Greyton
is currently inspecting the application and certifying over 200 NSW substations
being treated with Hilti, 3M and other products.
In the photos on the left, Greyton has constructed a Promatect H cable duct
consisting of 2 layers of 25mm H and 2 layers of 15mm H board. The top floor
section is Hebel block with a steel frame housing 9 access hatches for accessing
each part of the switch board The 80mm thick Promatect and Hebel will provided a
fully insulated system for a period of 2 hours and integrity for 4 hours. There
are a number of fire rated removable access hatches along the duct with safety
signage and heavy duty handles. This work can be viewed at
'Mechanical and Cable Duct Protection' . |
| |
| One.lend lease |
| |
This Lend Lease commercial development has been
built by Bovis Lend Lease. It is on Hickson road opposite the shipping
terminals. Greyton was contracted to carry out the vermiculite spray work to the
mechanical ventilation ducts including large fan enclosures constructed in a
Promatect solid board know as Promatect L500. Greyton also carried out other
fire protection systems such as the fire corridor ceilings using the same solid
Promatect board as used for the fan enclosures. This work can be viewed at
'Ceilings and Partitions' .
|
| |
| New Haymarket Sub station |
| |
This
project involved sealing of major penetrations, installing Promatetct Walls and
Floor barriers, vermiculite spray and Hilti cable coatings. The project at a
total cost of $300,000 had to be handed over to Energy Australia/Transgrid in
just over a month. Although the schedule was extremely tight, Greyton finished
on time and to the total satisfaction to Siemens. This project is one of a
number undertaken by Greyton in the 'Sydney CBD and Inner Suburbs 132kV Cable
Project'. Greyton has also worked in the Ventillation Chamber, the Campbell
Street Substation and the Existing Surry Hills Substation. Our Clients included
Siemens, Energy Australia, Downer Engineering and GHD Engineering. Photos of the
works can be seen under 'Penetrations Seals' and 'Tunnel Specialists'.
Read the reference from Siemens. |
| |
| Civic Tower |
| |
This
tower has been built by Grocon over the old Masonic Building in Sydney. The
structure is predominantly steel with massive cantilever beams at the base to
carry the tower. Greyton was contracted to fire rate the entire steel structure
on every level. The product used is 'Cafco 300', a vermiculite plaster spray.
|
| |
| The Ikon Apartments |
| |
This Potts Point refurbishment is prominent on the Sydney skyline as one looks towards Wooloomooloo. The Mirvac development has required substantial steel upgrading on every floor which has been installed by Greyton's client, Tie Fabrications. There is a combination of Intumecent Paint and Vermiculite spray application to the steel providing 1 to 2 hour FRLs. Greyton has also been awarded the mechanical duct fire rating contract by Allstaff Airconditioning. This involves vermiculite spray to ducts, fan enclosures in Promat board as well as some unusual work converting an existing lift well to a mechanical duct riser. The systems are to be fire separated in this case and two 19 story fire barriers will be installed by Greyton which will be achieved with a vermiculite barrier system. |
| |
| King Street Wharf Office Tower |
| |
|
This latest edition to the King Street Wharf development by Multiplex involves some major mechanical duct systems including multiple Kitchen exhaust systems. Greyton has been contracted by JL Williams to undertake this project with large duct runs and fans. The ducts will be sprayed with Vermiculite while fans will be housed in fire rated enclosures. These enclosures will be constructed in Promatect L500 calcium silicate boards. Other works include sealing of electrical penetrations for Roles Electrical.
|
| |
| Shore Apartments 6/7 and 8/9 |
| |
|
Currently underway this heritage redevelopment is being carried out by Mirvac and Transfield and has offered some significant challenges for Greyton. The main works involved removing lead paint from existing steel facade beams and fire rating them with Intumescent Paint. This process has been detailed under 'Steel Protection'. The FRL requirement was 2 hours which meant achieving a dry film thickness of up to 4mm in some areas. Other works completed include joint sealing, Vermiculite spray to steel and ducts, sealing of services penetrations and constructing fire rated bulk-heads in calcium silicate boards.
|
| |
| Sydney Theatre |
| |
|
Greyton is almost complete with all works for Barclay Mowlem on this latest addition to Sydney's theatres. This new state-of-the-art theatre is surrounded by heritage buildings that were used for storage of grain, wool, etc at the old docks around the turn of the century. The Bond Store buildings as they are known were constructed with timber floors supported by heavy cast iron columns shipped in from the UK. The fire protection of some 60 of these columns was the task of Greyton and maintaining the heritage appearance was the goal. There was also a substantial amount of new structural steel installed to support the renovations and this was all protected with Intumescent Paint, providing a 2 hour FRL. Vermiculite spray was used on three huge heritage beams that spanned over 30m between Bond 2 and 3 with a depth of 1.8m.
|
| |
| CSIRO Building |
| |
This project was completed in late 2002 by John Holland Constructions. The extent of Greyton's work mainly involved large penetration seals which carried large pipes between the floors and laboratories. Greyton was also contracted to carry out Vermiculite spray application to the mechanical duct work as well as some structural steel protection. |
 |